Which of the following are Agile Process Models ?
(A) Extreme Programming (XP)
(B) Waterfall
(C) Scrum
(D) Spiral
(E) Incremental
Pick an option to check yourself, or open the answer below.
Show answer & explanation
Correct answer: A. (A) and (C) Only
Explanation
Extreme Programming and Scrum are agile methods. Waterfall, spiral and incremental are traditional, plan-driven models.