Unit 6 · Software Engineering Paper 2 CS · June 2024 (Re-Exam)

Which of the following are typical activities in the software process lifecycle?

(A) Requirement Analysis

(B) System Design

(C) Code Refactoring

(D) Deployment

(E) Substructure

Pick an option to check yourself, or open the answer below.

Show answer & explanation

Correct answer: C. (A), (B), (D) Only

Explanation

Requirement analysis, system design and deployment are standard life-cycle activities. Refactoring is a coding practice inside implementation, and 'substructure' is not a phase.