Unit 6 · Software Engineering Paper 2 CS · June 2024 (Cancelled)

The ratio of errors found before s/w delivery and to the total errors (before and after) is called :

Pick an option to check yourself, or open the answer below.

Show answer & explanation

Correct answer: C. Defect Removal efficiency

Explanation

DRE = E / (E + D), where E is errors found before delivery and D defects found after.