Match List I with List II. List I: A. PERT, B. Optimistic time, C. CPM, D. Pessimistic time. List II: I. Used for non-repetitive jobs, II. Used for repetitive jobs, III. The shortest possible time to complete the activity if all goes well, IV. The longest time that an activity takes.

Pick an option to check yourself, or open the answer below.
Show answer & explanation
Correct answer: D. A-I B-III C-II D-IV
Explanation
PERT is used for non-repetitive (one-off, uncertain) projects; CPM for repetitive ones. Optimistic time is the shortest possible time, pessimistic time the longest.
More Software Engineering questions
- Match List I with List II. List I: A. Scenario testing, B. Regression testing, C. Component testing, D. Beta testing. List II: I. To verify…
- The time between failures for a software system is: failure 1 – 6 hours, failure 2 – 4 hours, failure 3 – 8 hours, failure 4 – 5 hours, fai…
- Given below are two statements: Statement I: subsystem models show logical grouping of objects into coherent subsystem Statement II: State…
- Which of the following is not one of the principles of good coding?
- If P is the risk probability, L is the loss, then Risk exposure (RE) is computed as ______
- The cyclomatic complexity metric provides the designer with information regarding the number of -____