Arrange the following phases of the Agile process in the correct sequence :
(A) Design
(B) Release
(C) Testing
(D) Development
(E) Planning
Pick an option to check yourself, or open the answer below.
Show answer & explanation
Correct answer: C. (E), (A), (D), (C), (B)
Explanation
An agile iteration runs planning, design, development, testing and then release.
More Software Engineering questions
- Which of the following are typical activities in the software process lifecycle? (A) Requirement Analysis (B) System Design (C) Code Refact…
- Match List - I with List - II.
- Match List - I with List - II.
- Arrange the following so that they can be placed in perfect/appropriate order. A. Planning C. Modeling B. Construction E. Deployment D. Com…
- The ratio of errors found before s/w delivery and to the total errors (before and after) is called :
- Which of the following is not the goal of reverse Engineering?