Identify the correct statements from the following regarding spiral model.
A. Spiral model is an incremental process model.
B. Spiral model is a risk - driven process mode.
C. Spiral model is an acyclic balancing approach.
D. Spiral model involves a set of anchor point milestone.
Choose the correct answer from the options given below:
Pick an option to check yourself, or open the answer below.
Show answer & explanation
Correct answer: D. B & D Only x y
Explanation
Boehm's spiral model is risk-driven and uses anchor-point milestones. It is classed as an evolutionary model and is a cyclic approach, so A and C are wrong.
More Software Engineering questions
- Collaborative document inspection technique used for?
- Which one of the following is not the part of requirement management?
- The characteristics of modern programming are : A. Each module should do only one thing. B. Communication between modules is allowed only b…
- Arrange the following steps of Feature Drive Development (FDD) process in the correct sequence : (A) Develop an overall model (B) Build by…
- Which of the following are Agile Process Models ? (A) Extreme Programming (XP) (B) Waterfall (C) Scrum (D) Spiral (E) Incremental
- Arrange the following phases of the Agile process in the correct sequence : (A) Design (B) Release (C) Testing (D) Development (E) Planning