Match List I (software risk) with List II: A. Predictable risk, B. Business risk, C. Project risk, D. Past risk. List II: I. Strategic risk, II. Staffing and organization, III. Implementation, IV. Past project experience.
Pick an option to check yourself, or open the answer below.
Show answer & explanation
Correct answer: D. A-IV, B-I, C-II, D-III
Explanation
Predictable risks are extrapolated from past project experience; business risks include strategic risk; project risks include staffing and organization problems; the remaining pairing (past risk – implementation) follows the official key.
More Software Engineering questions
- Identify the correct statements from the following regarding spiral model. A. Spiral model is an incremental process model. B. Spiral model…
- Collaborative document inspection technique used for?
- Which one of the following is not the part of requirement management?
- The characteristics of modern programming are : A. Each module should do only one thing. B. Communication between modules is allowed only b…
- Arrange the following steps of Feature Drive Development (FDD) process in the correct sequence : (A) Develop an overall model (B) Build by…
- Which of the following are Agile Process Models ? (A) Extreme Programming (XP) (B) Waterfall (C) Scrum (D) Spiral (E) Incremental