Which of the following are typical activities in the software process lifecycle?
(A) Requirement Analysis
(B) System Design
(C) Code Refactoring
(D) Deployment
(E) Substructure
Choose the correct answer from the options given below:
Pick an option to check yourself, or open the answer below.
Show answer & explanation
Correct answer: C. (A), (B), (D) Only
Explanation
Standard SDLC activities are requirements analysis, design, implementation, testing, deployment and maintenance. Code refactoring is a coding practice and 'substructure' is not an activity.More Software Engineering questions
- Match List I (software design principles) with List II (Definition)List I List II (A) Cohesion (I) Degree to which one module relies on ano…
- Given a project with an estimated effort of 1500 person-hours and a team of 5 people, how many days will it take to complete the project if…
- In software configuration management, what is the primary purpose of version control?
- Match List I (Testing Type) with List II (Description)List I List II (A) Unit testing (I) Testing individual components of the software. (B…
- Given a project that uses the COCOMO model with an estimated effort of 2000 person-months and a productivity rate of 5 person-months per KL…
- A test suite consists of: