Given a project that uses the COCOMO model with an estimated effort of 2000 person-months and a productivity rate of 5 person-months per KLOC, what is the estimated size of the project in KLOC?
Pick an option to check yourself, or open the answer below.
Show answer & explanation
Correct answer: B. 400
Explanation
Size = effort / (effort per KLOC) = 2000 / 5 = 400 KLOC.More Software Engineering questions