Unit 6 · Software Engineering Paper 2 CS · June 2024 Re-Exam

Given a project with an estimated effort of 1500 person-hours and a team of 5 people, how many days will it take to complete the project if each person works 8 hours a day?

Pick an option to check yourself, or open the answer below.

Show answer & explanation

Correct answer: B. 37.5

Explanation

Team capacity = 5 × 8 = 40 person-hours/day. Days = 1500 / 40 = 37.5.