Given a project with an estimated effort of 1500 person-hours and a team of 5 people, how many days will it take to complete the project if each person works 8 hours a day?
Pick an option to check yourself, or open the answer below.
Show answer & explanation
Correct answer: B. 37.5
Explanation
Team capacity = 5 × 8 = 40 person-hours/day. Days = 1500 / 40 = 37.5.More Software Engineering questions