If a software project has 2000 lines of code (LOC) and the average productivity rate is 10 LOC per person-hour, how many person-hours are required to complete the project?
Pick an option to check yourself, or open the answer below.
Show answer & explanation
Correct answer: C. 200
Explanation
Effort = size / productivity = 2000 / 10 = 200 person-hours.More Software Engineering questions
- Which of the following are typical activities in the software process lifecycle? (A) Requirement Analysis (B) System Design (C) Code Refact…
- Match List I (software design principles) with List II (Definition)List I List II (A) Cohesion (I) Degree to which one module relies on ano…
- Given a project with an estimated effort of 1500 person-hours and a team of 5 people, how many days will it take to complete the project if…
- In software configuration management, what is the primary purpose of version control?
- Match List I (Testing Type) with List II (Description)List I List II (A) Unit testing (I) Testing individual components of the software. (B…
- Given a project that uses the COCOMO model with an estimated effort of 2000 person-months and a productivity rate of 5 person-months per KL…