Which of the following are the primary objectives of risk monitoring in software project tracking? P : To assess whether predicted risks do, in fact, occur Q : To ensure that risk aversion steps defined for the risk are being properly applied R : To collect information that can be used for future risk analysis
Pick an option to check yourself, or open the answer below.
Show answer & explanation
Correct answer: D. All of P,Q,R
Explanation
Risk monitoring checks whether predicted risks occur, ensures aversion steps are applied, and gathers data for future risk analysis.
More Software Engineering questions
- Software validation mainly checks for inconsistencies between
- Which of the following statements is/are false? P: The clean-room strategy for software engineering is based on the incremental software pr…
- Consider the following method: int f(int m, int n, boolean x, boolean y) { int res = 0; if (m < 0) { res = n − m; } else if (x || y) { res…
- For a software system P: estimated size 33,480 LOC; average productivity 620 LOC per person-month; 6 developers; average salary ₹50,000 per…
- Match the following in Software Engineering :
- A software system crashed 20 times in the year 2017 and for each crash, it took 2 minutes to restart. Approximately, what was the software…