All mock tests are FREE till 31 December — register to save your progress
Unit 6 · Software Engineering Paper 2 CS · June 2019

Which of the following are the primary objectives of risk monitoring in software project tracking? P : To assess whether predicted risks do, in fact, occur Q : To ensure that risk aversion steps defined for the risk are being properly applied R : To collect information that can be used for future risk analysis

Pick an option to check yourself, or open the answer below.

Show answer & explanation

Correct answer: D. All of P,Q,R

Explanation

Risk monitoring checks whether predicted risks occur, ensures aversion steps are applied, and gathers data for future risk analysis.

More Software Engineering questions