For a software system P: estimated size 33,480 LOC; average productivity 620 LOC per person-month; 6 developers; average salary ₹50,000 per month. If E, D and C are the estimated effort (person-months), development time (months) and cost (₹ lakh), then (E, D, C) =
Pick an option to check yourself, or open the answer below.
Show answer & explanation
Correct answer: B. (54, 9, 27)
Explanation
E = 33,480/620 = 54 person-months; D = 54/6 = 9 months; C = 54 × 50,000 = ₹27 lakh.
More Software Engineering questions
- Match the following in Software Engineering :
- A software system crashed 20 times in the year 2017 and for each crash, it took 2 minutes to restart. Approximately, what was the software…
- Match the 5 CMM Maturity levels/CMMI staged representations in List- I with their characterizations in List-II
- Consider the following method: int f(int m, int n, boolean x, boolean y) { int res = 0; if (m < 0) { res = n − m; } else if (x || y) { res…
- Which of the following statements is/are false? P: The clean-room strategy for software engineering is based on the incremental software pr…
- Software validation mainly checks for inconsistencies between