Match List I (process models) with List II (systems). List I: (a) Waterfall model, (b) Incremental development, (c) Prototyping, (d) RAD. List II: (i) e-business software that starts with basic functionality and then moves to advanced features, (ii) An inventory control system for a supermarket to be developed within three months, (iii) A virtual reality system for simulating vehicle navigation on a highway, (iv) Automating the manual student record system of a school.

Pick an option to check yourself, or open the answer below.

Show answer & explanation

Correct answer: D. (a)-(iv); (b)-(i); (c)-(iii); (d)-(ii)

Explanation

Well-understood record automation suits waterfall; e-business growing feature by feature suits incremental; an unclear VR system suits prototyping; a 3-month inventory system suits RAD.