As per the Software Engineering Institute (SEI) Capability Maturity Model, the correct sequence is
A. Initial
B. Repeatable
C. Managed
D. Optimizing
E. Defined
Choose the correct answer from the options given below:

Pick an option to check yourself, or open the answer below.

Show answer & explanation

Correct answer: B. A, B, E, C, D

Explanation

CMM levels: 1 Initial, 2 Repeatable, 3 Defined, 4 Managed, 5 Optimizing.