A Software project was estimated at 864 Function Points. A six person team will be assigned to project consisting of a requirement gathering person, one designer, two programmers and two testers. The salary of the designer is ₹ 70,000 per month, requirement gatherer is ₹ 50,000 per month, programmer is ₹ 60,000 per month and a tester is ₹ 60,000 per month. Average productivity for the team is 12 FP per person month. Which of the following represents the projected cost of the project?
Pick an option to check yourself, or open the answer below.
Show answer & explanation
Correct answer: B. ₹ 43,20,000
Explanation
Effort = 864 / 12 = 72 person-months, i.e. 12 months for 6 people. Monthly team cost = 50k + 70k + 2×60k + 2×60k = 3,60,000. Total = 12 × 3,60,000 = ₹43,20,000.
More Software Engineering questions
- Software reliability is described with respect to (A) Execution Time (B) Calendar Time (C) Clock Time
- To create an object-behavioral model, the analyst performs the following steps: (A) Evaluates all use-cases (B) Builds state transition dia…
- Which of the following is/are behavioral testing technique(s)? (A) Equivalence Partitioning (B) Graph-Based Teating Method (C) Boundery Val…
- Match List I (CMM levels) with List II. List I: A. INITIAL, B. REPEATABLE, C. DEFINED, D. MANAGED. List II: I. Process measurement, II. Pro…
- In a system for a restaurant, the main scenario for placing an order is given below : (a) Customer reads menu (b) Customer places order (c)…
- An --------------- chart is a project schedule representation that presents project plan as a directed graph. The critical path is---------…