All mock tests are FREE till 31 December — register to save your progress
Unit 6 · Software Engineering Paper 2 CS · December 2019

An --------------- chart is a project schedule representation that presents project plan as a directed graph. The critical path is--------------- the sequence of ---------------tasks and it defines project---------------

Pick an option to check yourself, or open the answer below.

Show answer & explanation

Correct answer: B. Activity, Longest, Dependent, Duration

Explanation

An activity (network) chart shows the plan as a directed graph; the critical path is the longest sequence of dependent tasks and defines the project's duration.

More Software Engineering questions