An --------------- chart is a project schedule representation that presents project plan as a directed graph. The critical path is--------------- the sequence of ---------------tasks and it defines project---------------
Pick an option to check yourself, or open the answer below.
Show answer & explanation
Correct answer: B. Activity, Longest, Dependent, Duration
Explanation
An activity (network) chart shows the plan as a directed graph; the critical path is the longest sequence of dependent tasks and defines the project's duration.
More Software Engineering questions
- According to ISO 9126, match List I with List II. List I: (a) Functionality, (b) Reliability, (c) Efficiency, (d) Maintainability. List II:…
- Match the agile process models with their tasks. List I: (a) Scrum, (b) Adaptive software development, (c) Extreme programming, (d) Feature…
- The sequence diagram given in Figure 1 for the Weather Information System takes place when an external system requests the summarized data…
- How many nodes are there in flowgraph F?
- What is the cyclomatic complexity of flowgraph F?
- How many regions are there in flowgraph F ?