Match List I (CMM levels) with List II. List I: A. INITIAL, B. REPEATABLE, C. DEFINED, D. MANAGED. List II: I. Process measurement, II. Process definition, III. Project management, IV. Ad hoc.
Pick an option to check yourself, or open the answer below.
Show answer & explanation
Correct answer: C. A-IV, B-III, C-II, D-I
Explanation
Initial is ad hoc; Repeatable adds basic project management; Defined adds process definition; Managed adds process measurement.
More Software Engineering questions
- In a system for a restaurant, the main scenario for placing an order is given below : (a) Customer reads menu (b) Customer places order (c)…
- An --------------- chart is a project schedule representation that presents project plan as a directed graph. The critical path is---------…
- According to ISO 9126, match List I with List II. List I: (a) Functionality, (b) Reliability, (c) Efficiency, (d) Maintainability. List II:…
- Match the agile process models with their tasks. List I: (a) Scrum, (b) Adaptive software development, (c) Extreme programming, (d) Feature…
- The sequence diagram given in Figure 1 for the Weather Information System takes place when an external system requests the summarized data…
- How many nodes are there in flowgraph F?