Unit 2 · Computer System Architecture Paper 2 CS · September 2022

A 4-stage pipeline has stage delays of 150, 120, 160 and 140 ns. The registers between stages have a delay of 5 ns. Assuming a constant clocking rate, the total time required to process 1000 data items on this pipeline is

Pick an option to check yourself, or open the answer below.

Show answer & explanation

Correct answer: B. 165.5 ms

Explanation

Clock period = slowest stage + latch delay = 160 + 5 = 165 ns. Time for 1000 items = (4 + 999) × 165 ns ≈ 165.5 μs.

Note: The computed time is 165.5 μs; the options say ms.