Which one of the following is the correct estimation model based on the software equation?
Pick an option to check yourself, or open the answer below.
Show answer & explanation
Correct answer: B. E = [LOC × B0.333 / P]3 × (1/t4)
Explanation
Putnam's software equation (Pressman) gives effort E = [LOC × B0.333 / P]3 × (1/t4), where B is a special-skills factor, P a productivity parameter and t the project duration.More Software Engineering questions
- Software testability is simply how easily a software program can be tested. Which one of the following characteristics does NOT lead to tes…
- Identify the correct statements from the following regarding the spiral model. A. The spiral model is an incremental process model. B. The…
- The collaborative document inspection technique is used for?
- Which one of the following is NOT a part of requirement management?
- As per the Software Engineering Institute (SEI) Capability Maturity Model, the correct sequence is A. Initial B. Repeatable C. Managed D. O…
- The characteristics of modern (modular) programming are: A. Each module should do only one thing. B. Communication between modules is allow…