Which of the following is used to determine the cost performance index (CPI)?

Pick an option to check yourself, or open the answer below.

Show answer & explanation

Correct answer: C. Budgeted cost of work performed ÷ actual cost of work performed

Explanation

CPI = BCWP / ACWP (earned value / actual cost). BCWP − ACWP is the cost variance.