Match List I with List II
| List I | List II |
|---|---|
| A. PERT | I. Used for non-repetitive jobs |
| B. Optimistic time | II. Used for repetitive jobs |
| C. CPM | III. The shortest possible time to complete the activity if all goes well |
| D. Pessimistic time | IV. The longest time that an activity takes |
Pick an option to check yourself, or open the answer below.
Show answer & explanation
Correct answer: D. A-I, B-III, C-II, D-IV
Explanation
PERT is used for non-repetitive (one-off) jobs (I). Optimistic time is the shortest time if all goes well (III). CPM is used for repetitive jobs (II). Pessimistic time is the longest time an activity takes (IV).More Software Engineering questions
- Which of the following is used to determine the cost performance index (CPI)?
- ______ is intended to show that a system both conforms to its specification and meets the expectations of the system customer.
- Match List I with List IIList I List II A. Scenario testing I. To verify the I/O behaviour of a test object B. Regression testing II. User…
- Consider the following statements about a software product-line system: Statement I: At the interaction level, components provide an operat…
- An observational technique that can be used to understand operational processes and help derive requirements for software to support those…
- Consider a popular sports news site. At a given moment, 20,000 concurrent users each submit a request (a transaction T) once every 2 minute…