All mock tests are FREE till 31 December — register to save your progress
Unit 6 · Software Engineering Paper 2 CS · June 2023

Match List I with List II
List IList II
A. PERTI. Used for non-repetitive jobs
B. Optimistic timeII. Used for repetitive jobs
C. CPMIII. The shortest possible time to complete the activity if all goes well
D. Pessimistic timeIV. The longest time that an activity takes

Pick an option to check yourself, or open the answer below.

Show answer & explanation

Correct answer: D. A-I, B-III, C-II, D-IV

Explanation

PERT is used for non-repetitive (one-off) jobs (I). Optimistic time is the shortest time if all goes well (III). CPM is used for repetitive jobs (II). Pessimistic time is the longest time an activity takes (IV).

More Software Engineering questions