Which of the following is not a 'concern' during management of a software project?

Pick an option to check yourself, or open the answer below.

Show answer & explanation

Correct answer: A. Project/Product information

Explanation

Software project management is classically organised around the measurable constraints of a project — the time taken (schedule), the money spent (cost/budget) and the quality delivered — which together with scope form the standard project-management trade-off triangle. 'Project/Product information' is not itself a management constraint or concern; it is simply descriptive data about the project, not something that project management actively tracks and trades off the way it does time, cost and quality. Therefore, of the given choices, Project/Product information is the one that is not a genuine management concern.