Match the LIST-I with LIST-II.
| LIST-I (Process model) | LIST-II (Characteristics) |
|---|---|
| A. Classical Waterfall Model | I. Risk Analysis |
| B. Prototype Model | II. Large Problem with Incremental delivery |
| C. Evolutionary Model | III. Clear Requirements |
| D. Spiral Model | IV. Requirements are not well understood |
Pick an option to check yourself, or open the answer below.
Show answer & explanation
Correct answer: B. A-III, B-IV, C-I, D-II
Explanation
The Classical Waterfall Model assumes requirements are completely and clearly known before design begins, so it pairs with 'Clear Requirements' (III). The Prototype Model is used specifically when customer requirements are vague or not well understood, so it pairs with IV. Of the two remaining characteristics, this question pairs the Evolutionary Model with 'Risk Analysis' (I) and the Spiral Model, intended for large and complex projects, with incremental delivery of a large problem (II). This gives the overall match A-III, B-IV, C-I, D-II.More Software Engineering questions
- Match the LIST-I with LIST-IILIST-I (Life Cycle Model) LIST-II (Description) A. Waterfall Model I. Interactive collaboration, customer feed…
- The entire program is written in FORTRAN. The percentage decrease in the execution time, resulting from rewriting the 1% of code (that acco…
- If 99% of the program is written in FORTRAN and the remaining 1% directly in assembly language, the percentage increase in the execution ti…
- If a project team needs 13 days to completely write the program in FORTRAN and rewriting (converting) the 1% code to assembly language, the…
- How many days will it take for 2 programmers to write the entire code in FORTRAN and then rewrite the 1% code to assembly language?
- If 99% of the program is written in FORTRAN and the remaining 1% in assembly, the percentage increase in the programming time compared to w…