Software project manager is responsible for the following tasks:
A. Project Planning
B. Project status tracking
C. Resource management
D. Risk management
E. Project delivery within time & budget.
Pick an option to check yourself, or open the answer below.
Show answer & explanation
Correct answer: A. All the statements are correct.
Explanation
A software project manager plans the project, tracks status, manages resources and risks, and is responsible for delivering on time and within budget. All five are correct.
More Software Engineering questions
- Mr. X designed open source software which must comply with some criteria. Choose the false statement in respect of the above. 1. No restric…
- Match List I with List II
- Given below are two statements: one is labeled as Assertion A and the other is labeled as Reason R. Assertion A: Cohesion is a qualitative…
- Which metrics are derived by normalizing quality and/or productivity measures by the size of the software produced?
- The model in which the requirements are implemented by category is
- Modules X and Y operate on the same input and output data. The cohesion is