Unit 6 · Software Engineering UGC NET January 2017

A software project was estimated at 352 Function Points (FP). A four person team will be assigned to this project consisting of a project manager who will be paid ₹80,000 per month, two programmers who will be paid ₹60,000 per month each and one tester who will be paid ₹50,000 per month. The average productivity for the team is 8 FP per person month. Which of the following represents the projected cost of the project?

Pick an option to check yourself, or open the answer below.

Show answer & explanation

Correct answer: D. (D) ₹27,50,000