Unit 6 · Software Engineering UGC NET January 2017

A software company needs to develop a project that is estimated as 1000 function points and is planning to use JAVA as the programming language whose approximate lines of code per function point is accepted as 50. Considering a = 1.4 as multiplicative factor, b = 1.0 as exponential factor for the basic COCOMO effort equation and c = 3.0 as multiplicative factor, d = 0.33 as exponential factor for the basic COCOMO duration equation, approximately how long does the project take to complete?

Pick an option to check yourself, or open the answer below.

Show answer & explanation

Correct answer: B. (B) 12.2 months

More Software Engineering questions