Gantt charts are used in .......... phase.
गैंट चार्ट का उपयोग .......... चरण में किया जाता है।
Pick an option to check yourself, or open the answer below.
Show answer & explanation
Correct answer: B. Planning
Explanation
A Gantt chart is a bar chart of tasks against time, used in project planning and scheduling to show start and end dates, durations and overlaps.
गैंट चार्ट कार्यों को समय के विरुद्ध बार के रूप में दिखाता है — इसका उपयोग प्रोजेक्ट की योजना/शेड्यूलिंग में (आरंभ-समाप्ति तिथि, अवधि) किया जाता है।
More Software Engineering questions
- .......... is a collection of methodologies that emerged in response to the weakness of waterfall model development and its variations.
- In .......... the test plan is developed directly from the program specification and several test cases are developed from it.
- Which phase answers the questions of who will use the system, what the system will do and where and when it will be used ?
- Full form of MVC is :
- Project size is related with :
- The ............ phase of the system decides how the system will operate in terms of hardware, software and network infrastructure.