Arrange the following activities to form a general software engineering process model : (a) Modelling (b) Planning (c) Deployment (d) Construction (e) Communication
एक सामान्य सॉफ्टवेयर इंजीनियरिंग प्रक्रिया मॉडल बनाने के लिए निम्नलिखित गतिविधियों का सुव्यवस्थित मिलान करें : (a) मॉडलिंग (b) प्लानिंग (c) डिप्लॉयमेंट (d) कंस्ट्रक्शन (e) कम्युनिकेशन
Pick an option to check yourself, or open the answer below.
Show answer & explanation
Correct answer: C. e, b, a, d, c
Explanation
Pressman's generic process framework: Communication → Planning → Modelling → Construction → Deployment = e, b, a, d, c.
प्रेसमैन का सामान्य प्रक्रिया ढाँचा: कम्युनिकेशन → प्लानिंग → मॉडलिंग → कंस्ट्रक्शन → डिप्लॉयमेंट = e, b, a, d, c।
More Software Engineering questions
- In which stage individual components are integrated and ensured that they are error free to meet customer requirements ?
- Which of the following testing is also known as white-box testing ?
- Which is the step in waterfall model that involves a meeting with the customer to understand the requirements ?
- Which is not the right approach of incremental testing approach ?
- In context of software testing match of Column-I and Column-II is : Column-I Column-II i. Integration Testing a. Alpha Testing ii. Unit Tes…
- Consider Column-I and Column-II in context of tools to support UML diagram for analysis modeling : Column-I Column-II i. Power Designer a.…