All mock tests are FREE till 31 December — register to save your progress

Which one of the following is a highly associated activity of project planning?
(1) Keep track of the project progress.
(2) Compare actual and planned progress and costs.
(3) Identify the activities, milestones and deliverables produced by a project.

Pick an option to check yourself, or open the answer below.

Show answer & explanation

Correct answer: C. Identify the activities, milestones and deliverables produced by a project

Explanation

Project planning is the forward-looking activity of deciding what will be done: breaking the work down into activities, fixing the milestones that mark the end of each stage and listing the deliverables to be handed over. That is exactly option 3. Keeping track of progress (option 1) and comparing actual against planned progress and cost (option 2) are project monitoring and control activities, carried out after the plan exists and used to revise it. Since option 2 is not a planning activity, the combined option 4 is wrong too. The answer is identifying activities, milestones and deliverables.

More Data Structures and Algorithms questions