Which one of the following is a highly associated activity of project planning?
(1) Keep track of the project progress.
(2) Compare actual and planned progress and costs.
(3) Identify the activities, milestones and deliverables produced by a project.
Pick an option to check yourself, or open the answer below.
Show answer & explanation
Correct answer: C. Identify the activities, milestones and deliverables produced by a project
Explanation
Project planning is the forward-looking activity of deciding what will be done: breaking the work down into activities, fixing the milestones that mark the end of each stage and listing the deliverables to be handed over. That is exactly option 3. Keeping track of progress (option 1) and comparing actual against planned progress and cost (option 2) are project monitoring and control activities, carried out after the plan exists and used to revise it. Since option 2 is not a planning activity, the combined option 4 is wrong too. The answer is identifying activities, milestones and deliverables.More Data Structures and Algorithms questions
- Which of the following trees are height balanced? A. Binary Search Tree B. AVL Tree C. Red-Black Tree D. B Tree
- Which of the following algorithms use Greedy strategy? A. Dijkstra's algorithm B. Kruskal's algorithm C. Huffman coding D. Bellman-Ford alg…
- Match List I with List II
- Match List I with List II
- Considering the binary tree shown (A has children B and C; C has children D and E; E has right child F; F has children G and H), what will…
- Match the LIST-I with LIST-II