All mock tests are FREE till 31 December — register to save your progress
Unit 6 · Software Engineering UGC NET June 2023

Which of the following is used to determine the cost performance index?

Pick an option to check yourself, or open the answer below.

Show answer & explanation

Correct answer: C. (C) Budgeted cost of work performed ÷ Actual cost of work performed