Unit 6 · Software Engineering Paper 2 CS · September 2022

Which metrics are derived by normalising quality and/or productivity measures by the size of the software that has been produced?

Pick an option to check yourself, or open the answer below.

Show answer & explanation

Correct answer: D. Size-oriented metrics

Explanation

Size-oriented metrics normalise by size, e.g. errors per KLOC or cost per KLOC (Pressman).

More Software Engineering questions