Which metrics are derived by normalising quality and/or productivity measures by the size of the software that has been produced?
Pick an option to check yourself, or open the answer below.
Show answer & explanation
Correct answer: D. Size-oriented metrics
Explanation
Size-oriented metrics normalise by size, e.g. errors per KLOC or cost per KLOC (Pressman).More Software Engineering questions