The ratio of errors found before software delivery to the total errors (before and after delivery) is called:
Pick an option to check yourself, or open the answer below.
Show answer & explanation
Correct answer: C. Defect Removal Efficiency
Explanation
DRE = E / (E + D), where E is errors found before delivery and D is defects found after delivery.More Software Engineering questions
- Which of the following is NOT a goal of reverse engineering?
- The cyclomatic complexity of the following flow graph is: nodes 1, 2, 3, 4, 5, 6, 7, 9, 10 with edges 1→2, 1→10, 2→3, 2→4, 3→9, 4→5, 4→6, 5…
- Match List I with List IIList I List II A. Verification I. White box Testing B. Validation II. Black box Testing C. Internal logic exercise…
- Which of the following are white-box testing techniques? A. Path testing B. Loop testing C. Regression testing D. Non-functional testing Ch…
- For software quality assurance, which of the following is correct? A. Execution of code B. No execution of code C. Preventive technique D.…
- Which of the following is NOT one of the principles of good coding?