The cyclomatic complexity metric provides the designer with information regarding the number of ______
Pick an option to check yourself, or open the answer below.
Show answer & explanation
Correct answer: C. Independent logic paths in the program
Explanation
V(G) gives the number of independent paths, i.e. the size of the basis set for testing.More Software Engineering questions
- Statement I: Software testing must be recognised as a significant effort, and its planning must begin at the earliest possible time. Statem…
- Which of the following need not be assessed during unit testing? A. Algorithmic performance B. Number of lines of code C. Error handling D.…
- Match List I with List IIList I List II A. Condition coverage I. Black box testing B. Equivalence class partitioning II. System testing C.…
- The incremental model of software development is ____
- The primary objectives of the SWE-IPT (software engineering integrated product team) are to: A. Solicit stakeholder needs and expectations.…
- Which of the following is not a non-functional requirement?