A software project was estimated at 864 Function Points. A six-person team will be assigned to the project consisting of one requirement gathering person, one designer, two programmers and two testers. The salary of the requirement gatherer is Rs. 50,000 per month, the designer Rs. 70,000 per month, and each programmer and each tester Rs. 60,000 per month. The average productivity for the team is 12 Function Points per person-month. Which of the following represents the projected cost of the project?

Pick an option to check yourself, or open the answer below.

Show answer & explanation

Correct answer: B. Rs. 43,20,000

Explanation

Total effort = 864 FP ÷ 12 FP per person-month = 72 person-months.
With a six-person team working together, duration = 72 ÷ 6 = 12 months.
Monthly salary bill = 50,000 (requirement gatherer) + 70,000 (designer) + 2 × 60,000 (programmers) + 2 × 60,000 (testers) = 50,000 + 70,000 + 1,20,000 + 1,20,000 = Rs. 3,60,000 per month.
Projected cost = 3,60,000 × 12 = Rs. 43,20,000, which is option 2.