How do you create agile processes to manage unpredictability?
(A) Requirements gathering must be conducted very carefully
(B) Risk analysis must be conducted before planning takes place
(C) Software increments must be delivered in short time periods
(D) Software processes must not adapt to changes incrementally
Pick an option to check yourself, or open the answer below.
Show answer & explanation
Correct answer: C. (C) only
Explanation
Agility copes with unpredictability by shortening the feedback loop, so the essential practice is that software increments must be delivered in short time periods — short iterations let the customer see working software early and let the plan be adjusted from real evidence. Statement (A) reflects the heavyweight, plan-driven belief that requirements can be pinned down up front, which agile explicitly rejects. Statement (B) puts risk analysis before planning as a one-off gate, whereas agile re-assesses risk every iteration. Statement (D) is the exact opposite of agility, since adapting incrementally to change is the core agile principle, so (C) only is correct.More Discrete Structures and Optimization questions
- RAD software process model stands for
- The model in which the requirements are implemented by its category is
- Match List-I with List-II: List-I (Software process model) (a) Waterfall model (b) Incremental development (c) Prototyping (d) RAD List-II…
- Which of the following statements is/are false? P: The clean-room strategy to software engineering is based on the incremental software pro…
- Which of the following is not one of the principles of agile software development method?
- Which of the following is not a key issue stressed by an agile philosophy of software engineering?